Project Guide
MerchandisingCritical Path

Critical Path (Time & Action)

Every order against its milestone plan — so a late lab dip is visible before it becomes a missed vessel

Live Orders

12

on the T&A calendar

On Track

42%

within 2 days of plan

At Risk

3

3–5 days behind

Critical

4

worst slip 35 days

Order ConfirmedCritical Merchandisingplan May 26, 2026actual May 26, 2026Completed
Fabric BookedCritical Sourcingplan Jun 02, 2026actual Jun 04, 2026 (+2d)Completed
Trims Booked Sourcingplan Jun 06, 2026actual Jun 08, 2026 (+2d)Completed
Lab Dip ApprovedCritical Merchandisingplan Jun 16, 2026actual Jun 18, 2026 (+2d)Completed
Fit Sample ApprovedCritical Samplingplan Jun 24, 2026actual Jun 25, 2026 (+1d)Completed
Import Licence ClearedCritical Customsplan Jul 02, 2026actual Jul 03, 2026 (+1d)Completed
PP Sample ApprovedCritical Samplingplan Jul 10, 2026In Progress
Fabric In-houseCritical Storesplan Jul 18, 2026Pending
Fabric QC Passed Qualityplan Jul 22, 2026Pending
Cutting StartCritical Cuttingplan Jul 28, 2026Pending
Sewing StartCritical Productionplan Aug 03, 2026Pending
Inline QC Clear Qualityplan Aug 13, 2026Pending
Final QC / AQL PassCritical Qualityplan Aug 21, 2026Pending
Packing CompleteCritical Packingplan Aug 25, 2026Pending
Ex-factoryCritical Logisticsplan Aug 29, 2026Pending
Vessel Cut-offCritical Logisticsplan Sep 02, 2026Pending

Vessel cut-off Sep 02, 2026 · comfortably inside the booking window

Ex-factory has four days of float before the booking is at risk.

Open Order